Furniture is one of the last things installed in a new restaurant and one of the first things that can delay an opening. This checklist walks through what to decide, and when, so seating arrives on time and fits the room.
Wood finish, metal finish and upholstery all need sign-off before production. Designform provides finish swatches and, for most products, an actual sample to sit in. Projects of 10 or more pieces can borrow up to two chair or stool samples through our sample loan program. If you are using your own fabric or leather, see COM and COL: the yardage and a swatch approval have to be in hand before production can start.
| Option | Typical lead time |
|---|---|
| Quick ship (in stock) | Ships in 2–3 days from order and payment |
| Custom order, rush | About 8–10 weeks for many products |
| Custom order, standard | 14–20 weeks |
Lead times start once finishes are approved and the order is placed, and they do not include freight or installation. If the opening date is close, start with quick ship items. Our lead times guide explains how to plan backward.
File the product cut sheets, finish selections and the warranty with your opening documents: 3 years on frame structural integrity and 1 year on finish and upholstery, from the ship date. See our warranty and care guide.
Lead times · Quick ship restaurant furniture · How much space per seat · Types of restaurant chairs
Send us your floor plan and opening date. Your local Designform rep can build the furniture list, send samples and tell you what ships in time.
Request a Quote / Samples