Furniture is one of the last things to arrive on a construction schedule and one of the first things blamed when an opening slips. The fix is simple in principle: work backwards from the date the doors open, not forwards from the date you place the order. Here are the real numbers to plan against.
If your date is tighter than any of these, tell us anyway. Sometimes we can do better, and it is always worth the call.
This is where schedules go wrong. Production time starts once the order is complete and approved. Add to your calendar, before production begins:
For a standard custom order opening in, say, 26 weeks:
Notice the float. If you plan to the minimum on every line, one slipped approval consumes it.
Comfort cannot be judged from a photograph, and a chair that looks right in a rendering can be wrong at the table. We provide finish swatches, and an actual product sample for most products so you can sit in it.
Our Sample Loan Program: for projects of 10 or more pieces, up to two chair or stool samples are complimentary and we pay shipping both ways. For projects under 10 pieces, the client covers shipping and sample charges. Samples are a 60-day loan with a credit card authorisation on file, returned in the original packaging with a prepaid label. Loan samples have been out before, so expect some cosmetic wear.
All seating ships fully assembled from our factory. Tables ship with tops and bases separate, with hardware provided, for the customer to attach. Plan a little labour for tables on install day, and plan levelling — almost no restaurant floor is flat.
Minimum order is typically 4 pieces per item, with smaller orders considered on request. We ship nationwide and to Canada, quick ship included.
Tell your rep the opening date at the first conversation, not at the end. Nearly every timeline problem we see could have been solved in week one by choosing a quick ship frame, a rush-eligible frame, or a standard upholstery instead of a COM. Once you are six weeks out, the options narrow to whatever is already on our floor.
COM and COL · How quick ship works · What BIFMA certification means
Working to a date? Contact your local sales rep or a project manager or administrator in our office with the date and the piece count, and we will tell you honestly what is achievable.
Tell us what you are furnishing. We will send pricing, finish options and samples, and connect you with your local Designform rep.
Request a Quote / Samples